Title : Evaluation of BOT Projects in Egypt: A
Case Study of Sidi Krier Power Station
Author : Engy Moustafa Abd El-Aal
Collection : M.Eng. Civil
Abstract:
There is no doubt that the Egyptian economy is going through
a very difficult circumstances as a result of the political situation of the
country, and due to the strategic importance of national projects which held by
BOT system it is important to study and analyze previous contracts and
agreements to determine negative aspects and to avoid that the government to
repeat these mistakes during the implementation of new projects of this system.
The research aims to identify the negatives in the previous BOT agreements in
Egypt and tills through the analysis of the project contracts of these previous
projects and analyzing the problems that occurred during these projects and
comparing it with what is happening in other countries such as China. It was so
clear to find many different malpractices in the application of such type
projects in Egypt compared to other countries. Also a comparison between the
clauses of the BOT contracts and what came in the FIDIC silver book. The
research stated many recommendations to overcome mistakes happened m previous
projects and hopping to avoid them in the future agreements.